A Review of Contract Awards to Lowest Bidder in Indian Construction Projects via Case Based Approach

HTML  XML Download Download as PDF (Size: 787KB)  PP. 159-168  
DOI: 10.4236/ojbm.2017.51015    2,341 Downloads   7,864 Views  Citations

ABSTRACT

Indian construction especially public sector organisations and government department mostly depends on lowest financial bidder for award of contracts. At some point time of these projects, it has become a common scenario that there is a schedule delay resulting in extension of time. So it can be mentioned that modern contract handling procedures require an overhauling. The study presents a case-based approach, in which authors have studied different projects that have been awarded on basis of financial criterion. Ultimately conclusions have been drawn by comparing efficiency of contractor with progress, ratio of bid and project cost and other factors.

Share and Cite:

Deep, S. , Singh, D. and Ahmad, S. (2017) A Review of Contract Awards to Lowest Bidder in Indian Construction Projects via Case Based Approach. Open Journal of Business and Management, 5, 159-168. doi: 10.4236/ojbm.2017.51015.

Cited by

[1] Dispute Avoidance in Public Construction Projects
Journal of Legal Affairs and Dispute …, 2023
[2] Efektivitas Komitmen Pengelolaan Risiko Lingkungan dan Sosial dalam Organisasi Penyedia Jasa Konstruksi
Semesta …, 2022
[3] A Suggested Tool for Boosting Efficiency of Donor Policy in Tenders of Construction Projects in Egypt
Port-Said Engineering Research Journal, 2021
[4] Identifying Challenges of Construction Industry in India.
… Online Journal of …, 2021
[5] A Model for Detection and Prevention of Unbalanced Bid in the Public Work Procurement Process in India
… and Technology Journal, 2021
[6] The Supply Chain Management Bid Process: An Examination of Proposal Response and Bidding Decisions
2021
[7] Assessment and Selection of Contractors in Specific Contracting Projects with Supply Chain Approach, Using GRAY and AHP Methods as Decision Support
2019
[8] Assessment and Selection of Contractors in Specific Contracting Projects with Supply Chain Approach, Using GRAY and AHP Methods as Decision …
2019
[9] Criticality of Construction Industry Problems in Developing Countries: Analyzing Malaysian Projects
2019
[10] The Impact of Lowest Bidding Bid Awarding System on Construction Project Quality in Gaza Strip. ةيسختلا ماعن خيثأت عيراذملا يف ةدؽجلا ىمع راعسلأا لقأ ىمع‎
2018
[11] An analytical study of critical factors affecting contractor efficiency in construction projects in Indian scenario
2018
[12] Identification of Delay Causing Actor in the Indian Real Estate Project: an AHP-Based Approach
Baltic Journal of Real Estate Economics and Construction Management, 2018
[13] Risk Management in Construction Projects
The International Journal of Engineering and Science, 2018
[14] Procurement with BIM: Lithuanian situation analysis and further development
Mokslas–Lietuvos ateitis/Science–Future of Lithuania, 2017
[15] A STUDY OF PROJECT SUCCESS AND PROCUREMENT FRAMEWORKS IN INDIAN CONSTRUCTION INDUSTRY
2017
[16] VIESIEJI PIRKIMAI SU BIM: LIETUVOS SITUACIJOS ANALIZE IR PERSPEKTYVOS
Science - Future of Lithuania, 2017
[17] Procurement with BIM: Lithuanian situation analysis and further development/Viešieji pirkimai su BIM: Lietuvos situacijos analizė ir perspektyvos
2017
[18] QUANTIZATION OF RISKS INVOLVED IN SUPPLY OF READY MIX CONCRETE IN CONSTRUCTION INDUSTRY IN INDIAN SCENARIO
2017
[19] RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
2017
[20] Review of Various Delay Causing Factors and Their Resolution by Application of Lean Principles in India
Baltic Journal of Real Estate Economics and Construction Management, 2017
[21] Construction Disputes In Construction Work Sites and Their Probable Solutions
2017
[22] A study of various factors affecting contractor's performance in lowest bid award construction projects
2017
[23] Earned Value based Liability Calculation Algorithm for Schedule Delays in Construction Projects
2017
[24] VIEŠIEJI PIRKIMAI SU BIM: LIETUVOS SITUACIJOS ANALIZĖ IR PERSPEKTYVOS
Mokslas - Lietuvos ateitis, 2017

Copyright © 2024 by authors and Scientific Research Publishing Inc.

Creative Commons License

This work and the related PDF file are licensed under a Creative Commons Attribution 4.0 International License.