Impacts of the Financial Factors on Schedule Delays Risk of the International Contracting Projects: Evidence from Highway BOT Pro-jects in Vietnam

HTML  XML Download Download as PDF (Size: 289KB)  PP. 311-319  
DOI: 10.4236/wjet.2015.34030    5,249 Downloads   6,752 Views  Citations

ABSTRACT

Vietnam has become a major market for construction enterprises from East Asian countries, especially from China, to participate in international project contracting, but serious schedule delays have important adverse effects on local government and foreign investment companies. Based on international engineering contracting mode of Vietnam highway BOT construction projects, we discussed the drive financial factors of schedule delays, using the methods of exploratory factor analysis and questionnaire survey, and evaluated the effects of various factors which are through regression analysis. The empirical results show that the five categories of financial factors, including the policy change, slow payment, financial mismanagement, financial market changes and lack of fiscal, have significant effects on schedule delay. Furtherly, we suggested that strengthening policy research and improving financial management ability should be used to reduce the influence of relevant financial factors on schedule delay, to improve the profitability of international businesses and the motivation of foreign enterprises to participate in Vietnam highway project.

Share and Cite:

Vu, H. , Wang, J. , Min, L. and Nguyen, T. (2015) Impacts of the Financial Factors on Schedule Delays Risk of the International Contracting Projects: Evidence from Highway BOT Pro-jects in Vietnam. World Journal of Engineering and Technology, 3, 311-319. doi: 10.4236/wjet.2015.34030.

Cited by

[1] Research on Interface Management of General Contracting Projects
World Journal of Engineering and Technology, 2022
[2] Impact of the use of incentives on project delivery in Ghana
2021
[3] Examining the Cash Flow Management Practices in the Construction Industry: A case of Pakistani Firms.
2021
[4] Effect of mismanagement towards abandoned project in Malaysia
2020
[5] The new politics of debts: perspectives from an emerging market
2018
[6] CEB Working Paper
2018
[7] How swelling debts give rise to a new type of politics in Vietnam
2018
[8] Performance Risks Allocation in Bot Infrastructure in Nigeria: A Case Study of Lagos Infrastructure Project
YBL Journal of Built Environment, 2017
[9] Risk analysis of schedule delays in international highway projects in Vietnam using a structural equation model
Engineering, Construction and Architectural Management, 2017
[10] Financial Risks Contributing to Delay of Oil and Gas Projects in Egypt
2016

Copyright © 2024 by authors and Scientific Research Publishing Inc.

Creative Commons License

This work and the related PDF file are licensed under a Creative Commons Attribution 4.0 International License.