
Run of River Bulk Hydroelectric Generation from the Congo River without a Conventional Dam
20
run of river application; fully allowing for Inga 1 and 2
continuous operation.
Over the last few years, two separate designs have
been proposed for the Inga 3 power station. The first was
prepared on the basis of an evolutionary design approach
to continue along the Inga 2 open channel design; here
more water was brought into the holding pools and an
Inga 3, a 3 600 MW station was proposed; 8 machines at
450 MW to yield a total of 3 600 MW, using 6 117 m³/
sec and with a natural head of 60 m. This was the Inga 3
allocated to WESTCOR for development.
A separate study by SNC Lavalin of Montreal pre-
pared another sitting of Inga 3 with a collection of un-
derground tunnels feeding the machines. Water is extr-
acted at a point above the holding pools and is fed di-
rectly into the machines; with a natural head of 100 m.
Here the planned output was 4 320 MW.
Both the 3 600 MW and the 4 320 MW design options
are available for development as the river has the capac-
ity to support both. The total is 7 920 MW and is well
within the constant flow of the river. For both options,
the designers should be challenged to increase both ca-
pacities to 5 000 MW such that even at 10 000 MW, we
still have a gap to the 12 959 MW first boundary limit.
Any drop in water flow will be reflected in an associated
drop in energy sent out and this will vary with time and
is manageable with system reserves.
2.2. Recommendation 2
The open channel design based on the Inga 2 concept is
named the Inga 3 Power Station.
Planned Capacity: 3 600 MW; 8 machines each of 450
MW rating; 60 m natural head
Design Challenge: 5 000 MW
2.3. Recommendation 3
The SNC Lavalin Study providing for a power station of
capacity of 4 320 MW and based on a collection of un-
derground tunnels at a natural head of 100m be named
Inga 4. This would be similar to Eskom Drakensberg
Power Station located in Bergville, South Africa [8].
Planned Capacity: 4 320 MW; 100 m natural head.
Design Challenge: 5 000 MW.
The sitting of both Inga 3 and Inga 4 is at different
points on the banks of the Congo River and work can
commence on sites simultaneously. There is a large physi-
cal separation between both power stations.
2.3.1. Scena ri o 4: The Co nventional D am
Preliminary analysis shows that the installation of a con-
ventional dam in the path of the river flow would have
the following potential impact on the natural environ-
ment:
1) The river flow is arrested and no water flows into
the ocean. At present, the river flows for many kilome-
ters into the ocean and thus fresh water is displaced
gradually with the salt water of the ocean. Halting fresh
water flow would have the reverse effect; the salt water
would intrude into the gap left by the fresh water stop-
page and the salt water would destroy all life dependent
on fresh water. The intrusion of the salt water would be
some 50 km inland and this would cause irreversible en-
vironmental harm to all living matter and organisms at
the river mouth.
2) Arresting the Congo River with its high and regular
flows would have the effect of pushing back the water
levels on the river itself. Much of Kinshasa and neighbor-
ring Congo Brazzaville through which the river passes
would be submerged by the rising water levels. Prelimi-
nary analysis of the land contours show a flat profile in
the immediate vicinity of the river and this would create
a massive lake that could stretch across Central Africa.
It is thus preferred that much of the river must con-
tinue to flow as naturally as possible; keeping the impact
on the environment to an absolute minimum. Once we
have exploited the full potential of the run of river capa-
bility, one could consider storage for those times when
the river flow is much higher than the normal constant
flow. This would afford a further development based
more on water retention only when such time permits and
then a further development of power generation capabil-
ity as in stored water when available. More work is nec-
essary to develop the concept of Grand Inga Cascades
rather than Grand Inga Dam. In the case of water cas-
cades, the same water could be employed several times
for power generation before being released back into the
river. With sound engineering, much more output can be
extracted with no impact on the environment.
3. Conclusions
The shareholder benefits from Inga 3 development sus-
tains and in summary, we have:
1) An annual income to the DRC Government of USD
500 m for the use of the water as primary energy.
2) Given natural, renewable energy employment, this
annual revenue flow to the DRC Government will occur
every year, indefinitely. In two years, this equates to
USD 1 billion; a substantial contribution that can go to-
wards developing the schools, hospitals, communities…
towards a better quality of life for all the people of the
DRC.
3) The delivery of the world’s lowest cost wholesale
tariff to all the five customers as in SNEL, ENE, Nam-
power, BPC and Eskom.
4) Payback of interest on capital and capital debt;
within 10 years WESTCOR will enjoy debt free assets
worth USD 5 billion.
C
opyright © 2011 SciRes. NR