Implementing an Information System Strategy: A Cost, Benefit, and Risk Analysis Framework for Evaluating Viable IT Alternatives in the US Federal Government

Abstract

In the US Federal government, an analysis of alternatives (AoA) is required for a significant investment of resources. The AoA yields the recommended alternative from a set of viable alternatives for the investment decision. This paper presents an integrated AoA and project management framework for analyzing new or emerging alternatives (e.g., Cloud computing), as may be driven by an information system strategy that incorporates a methodology for analyzing the costs, benefits, and risks of each viable alternative. The case study in this paper, about a business improvement project to provide public health and safety services to citizens in a US Federal agency, is a practical application of this integrated framework and reveals the benefits of this integrated approach for an investment decision. The decision making process in the framework—as an integrated, organized, and adaptable set of management and control practices—offers a defensible recommendation and provides accountability to stakeholders.

Share and Cite:

Espinoza, S. , Brooks, J. and Araujo, J. (2018) Implementing an Information System Strategy: A Cost, Benefit, and Risk Analysis Framework for Evaluating Viable IT Alternatives in the US Federal Government. International Journal of Communications, Network and System Sciences, 11, 105-132. doi: 10.4236/ijcns.2018.116007.

1. Introduction

At the US Centers for Disease Control and Prevention (CDC) and the Agency for Toxic Substances and Disease Registry (ATSDR), oversight of federal scientific regulations is housed in the Office of the Associate Director for Science (OADS) within the Office of the Director of CDC. Complying with these regulations is cumbersome and time consuming for scientists, programmatic staff, and the OADS personnel who must provide administrative oversight for achieving regulatory compliance. Unintended outcomes of this burden are risks associated with conducting public health science that cannot withstand peer review, public scrutiny, or audits. To achieve a goal of science regulation compliance, OADS committed to a business improvement project that would implement optimal processes, which in turn would serve downstream agency science and, ultimately, public health and safety. This business improvement project was titled the “Science Services Support Project” (S3P) [1].

The S3P business improvement project included the implementation of a new information technology (IT) system. In the US Department of Health and Human Services (DHHS), IT projects are subject to the Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC) [2] [3] which stipulates the implementation of the EPLC framework for managing IT projects. The major components of the framework are 10 phases marked by stage gate reviews, project reviews, and deliverables, as illustrated in Figure 1. During the second phase of the EPLC framework, projects must complete a business case, inclusive of an analysis of alternatives (AoA). The AoA sets the stage for the approach to a specific IT system implementation [4].

The US Office of Management and Budget (OMB) guidance in Circular A-11 [5] directs US agencies to develop an AoA for significant investments of resources. The underlying drivers of the AoA in the US and how the AoA should be developed and completed include legislation [6], policies [7], reviews [8], and practice guides [9]. In both civilian and non-civilian US agencies, the AoA is a standard effort and deliverable undertaken during an early phase of a project [4] [9] [10] [11] [12]. While the expectation is significant, the federal directives for conducting the AoA do not offer specific guidance for how to incorporate environmental drivers into the AoA for an IT system implementation, such as cloud computing.

In late 2010 and early 2011, the US Federal government announced its move to a “Cloud First” policy [7] [13]. This policy stated that “when evaluating options for new IT deployments, OMB will require that agencies default to cloud-based solutions whenever a secure, reliable, cost-effective cloud option exists” ( [7], p. 7). “Cloud First” was motivated by efficiency―a longstanding goal throughout the federal government related to the stewardship and accountability for public funds. While it is common to create a financial context around efficiency drivers for policies, the “Cloud First” policy had a broader impact agenda that also included reliability, innovation, and agility for information technology. For an IT project, the widest and deepest impact of this policy likely is experienced during the development of the business case for the project―and the included analysis of alternatives―because “Cloud First” automatically introduces an alternative into the AoA [7] [13] [14] [15] [16]. This means that the “Cloud

Figure 1. CDC adaptation of the DHHS EPLC framework [3].

First” policy is the requirement that Cloud computing must be considered when identifying potential alternatives in the AoA, and if the Cloud alternative is secure, reliable, and cost effective, then it must be the recommended alternative for the IT project. This predetermined yet conditional AoA outcome of “Cloud First” logically is linked to the principle of cost effective stewardship of public funds.

As noted, an AoA is more than a standard practice in the US Federal government: It is a requirement. Also, a Cloud alternative in an IT AoA would be expected, especially after the appearance of the “Cloud First” policy. The combination of these two requirements is not reflected in the literature; the current literature focuses on impediments to Cloud implementations versus the inclusion of the actual Cloud alternative, as might be expected from marrying “Cloud First” with federal directives for AoAs [17] - [22]. This observation with respect to the literature may indicate that the structured, decision making process of the AoA in federal practice, which ends up with a recommended alternative for delivering the IT Solution, does not have a logical articulation with “Cloud First”. Thus, while the US Federal government may adopt an information system strategy, such as “Cloud First”, methods, tools, and experience make initiatives possible that will achieve the goals established for the strategy. Our paper bridges the gap, or clears an impediment, between strategy and implementation by demonstrating how to incorporate an information system strategy into a decision for the initiative that will achieve the strategic goals of the organization.

Using a case study, our paper presents the integration of two frameworks for completing an AoA (i.e., the first framework) for an IT project (i.e., the second framework), inclusive of the OMB Cloud imperative, to address a science business need within an operating division of DHHS, to answer the questions of 1) what is the recommended alternative; and 2) should the recommended alternative be based on cloud computing. We specifically describe how Cloud computing (reflective of an environmental driver appearing in an information system strategy), as one of all possible alternatives, was included in the set of viable alternatives in the AoA framework. We also illustrate the integration of the AoA framework into the DHHS IT project management framework entitled the EPLC framework. The systematic integration of the AoA into the overarching IT project management approach makes it possible to accommodate environmental factors, such as Cloud computing, into the viable set of alternatives and achieve strategic goals of an information system strategy.

2. Description of the AoA Framework

The AoA framework, depicted in Figure 2 and overlapping the Initiation and Concept phases within the overarching EPLC framework for IT projects in DHHS, is best viewed as a set of methods and practices that can be tailored to serve the purposes of a specific IT project, as permitted by policy [3]. The “purposes” include new or emerging environmental factors, as was experienced by S3P when “Cloud First” appeared. Thus, the articulation of these two frameworks consists of the two concurrent work streams―AoA and overall project management work streams―during the early phases of an IT project in which this articulation provides cross cutting benefits (or advantages) to the concurrent work streams. Viewing the AoA as distinct and different from the overall project effort can lead to additional (duplicative) effort and reduced effectiveness of the AoA per se to effectively guide the project to success [8].

The AoA framework is divided into two primary sections: a section corresponding to work that logically and generally is a precursor to the AoA (i.e., Pre-AoA) and a section marked by the four signature phases of the AoA (i.e., the AoA per se or “Proper”). There is a distinction between the Pre-AoA and the AoA Proper because of the relationship between the AoA framework sections and the EPLC framework (see Figure 2). A benefit of following a systematic framework for completing an AoA is that it can provide a record of work leading to the recommended alternative. Such a record encourages or invites broad stakeholder scrutiny during the course of review, governance and decision making, and provides the basis for a defensible position vis-à-vis the recommended alternative.

Figure 2. The AoA framework for conducting an analysis of alternatives within the initiation and concept phases of the EPLC framework.

2.1. Pre-AoA: Assess Current Environment and Determine Future Environment Requirements

The Pre-AoA section of the framework encompasses two overarching processes: 1) assessing the current environment and 2) determining future environment requirements. These two Pre-AoA activities are inputs for creating a unified work stream composed of “Capability Modeling and Requirements Refinement”. This unified work stream provides a formal approach for establishing “what” must be resolved without the distraction of the “how”. “What” must be resolved is the gap between the current environment and the future requirements, and the objective of the AoA is to identify and recommend a solution that could close this gap, given the constraints of the project environment.

2.1.1. Assess Current Environment

The status quo environment comprises the existing IT systems and business processes that the proposed project intends to either enhance or replace, as they do not fully meet the current or future business needs. During the assessment of the current environment, project subject matter experts (SMEs) determine the operational gaps in the current environment by evaluating the degree to which the current state can support the identified high level business capabilities and business entities needed to support the future state.

The outputs of this process of assessing the current environment assist identification of business requirements and process models and inform the cost, benefit, and risk analyses of the alternatives in the second phase in the “Proper” section of AoA framework.

2.1.2. Determine Future Environment Requirements

In this process, the SMEs refine further the future environment requirements and business processes to articulate clearly what is required to meet the business need and achieve the strategic objectives for business success. The ongoing iterative examination of the desired future state serves to cement how each of the capabilities and entities will contribute to meeting the desired business need, allowing the business to drive the project requirements. The future requirements identified in this process have sufficient detail to support selecting and evaluating alternatives and then to recommend a solution.

2.2. AoA Proper: Framework for Analyzing Alternatives in IT Projects

The AoA Proper section of the framework has four signature phases that provide a systematic approach for conducting an analysis of alternatives for IT projects in the US Federal government. It is based on federal guidance documents and policies and incorporates knowledge from past CDC IT projects as well as government and industry best practices in the area of IT project management.

2.2.1. Phase 1: Identify and Filter Alternatives for Analysis

The first phase in the AoA consists in generating a set of possible alternatives that could satisfy the project business needs and then screening this set to identify only viable alternatives for further consideration in the subsequent phases of the framework.

1) Identify Possible Alternatives

The set of possible alternatives is comprised of alternatives that potentially could meet the future state requirements. While derived from classes of “automated solutions, tools, or products”, the proposed alternatives do not name specific vendors or actual technical solutions, because the project is working in the realm of the business need and has not advanced to the point where specific requirements exist that can lead to an analysis of alternative technical solutions. This initial set of alternatives begins with and must include the status quo [23]. The status quo alternative represents making no changes to the current system or environment and is the current baseline against which other alternatives are measured. This alternative always is carried forward to the next phase of the AoA for further analysis as the business owner always maintains the option of “doing nothing”. In addition to the status quo, alternative solutions can be identified based on a) “how” the solution will be obtained or procured and; b) the solution delivery framework (SDF) as encapsulated by a Cloud or a Non Cloud computing model. The four main options for how to obtain or procure a solution are:

a) Commercial Off-The-Shelf (COTS): A solution based on a commercially developed or proprietary product with configuration and/or customization to meet the business need.

b) Government Off-The-Shelf (GOTS): A solution based on a government developed product with configuration and/or customization to meet the business need.

c) Suite of Integrated Products and Services (SIPS): A solution based on a suite of integrated COTS and/or GOTS products and services, using configuration or customization. The SIPS solution also may integrate Open Source products.

d) Custom Build: A solution largely based on original, custom development and programming

The “Cloud First” policy introduces an SDF based on service and deployment models (see Table 1). The combinations between how a solution can be obtained (COTS, GOTS, SIPS or Custom Build) and the solution delivery framework generally represent all of the possible alternatives for an IT project.

2) Filtering for Viable Alternatives

The possible alternatives are narrowed down to a set of viable alternatives through a decision framework based on inputs from the Pre-AoA activities. The decision framework identifies the criteria by which alternatives will be excluded (or included) from further consideration and comprises two consecutive stages or filters.

Table 1. Cloud computing terminology.

Note. Adapted from The NIST Definition of Cloud Computing ( [24], p. 2-3). aApplication is defined as the end-user software functionality provisioned via the Cloud platform. bInfrastructure is defined as the underlying IT components, software and hardware, that support the essential characteristics of Cloud computing. cA provider is defined as an entity making available the essential characteristics of Cloud computing to a consumer organization. dOn-Premise is a computing model, Cloud or not, that deploys locally at the consumer organization. Off-Premise is a computing model, Cloud or not, that deploys remotely from the consumer organization.

Filter 1: Mandatory requirements. The first filter serves to identify the alternatives that conform to government mandatory requirements. These requirements may be the result of legislation or policies and their compliance by an alternative quickly establishes the feasibility of such an alternative. As an example, within the US Federal government, agencies must apply the Federal Information Processing Standards (FIPS) 199 security standards when determining the security category of their information systems [25]. If an alternative can satisfy all of the mandatory requirements, then it will continue on to the second filter; otherwise, it will be eliminated. The alternatives that pass the first filter are considered feasible.

Filter 2: Project-level requirements. The second filter evaluates the degree to which an alternative can satisfy a set of project-level decision criteria. The decision criteria are based on both functional and nonfunctional requirements. They are defined and assigned weights―representing the importance or priority of the criterion to the project―by the project SMEs, and then reviewed by the integrated project team (IPT), especially to establish an exclusion (or inclusion) threshold. Each feasible alternative is scored based on its ability to meet each of the decision criteria, and the weighted scores are calculated and aggregated to obtain a single overall score for each alternative followed by a determination to retain the feasible alternative as a viable alternative.

At the end of the two-step filtering process, at least three viable alternatives must remain, in addition to the current baseline or status quo alternative, to comply with Part 7 (Section 300) of the OMB Circular A-11 [15]. Each of the viable alternatives needs to be defined at a level of detail that can lead to estimates of costs, analysis of benefits, and assessments of risks in the subsequent phase of the AoA framework.

2.2.2. Phase 2: Conduct Cost, Benefit, and Risk Analysis of All Viable Alternatives

Once viable alternatives are identified, a more detailed analysis is conducted, which is composed of three separate yet related analyses: the cost analysis, benefit analysis, and risk analysis (see Figure 3). While each of these has a separate objective, the results of all of these analyses must be evaluated collectively to identify the recommended alternative.

The “Cost Analysis” section estimates the life cycle costs of each viable alternative for delivering the business IT solution that meets the project’s business needs. Because the cost analysis is an examination of the projected (or anticipated) life cycle costs, the model to calculate these costs is assumption-driven.

The “Benefits Analysis” section evaluates the anticipated benefits, both quantitative and qualitative, for each viable alternative. The quantitative benefits analysis evaluates the potential benefits of a given alternative following the same assumption-driven approach employed in the cost analysis. The analysis of the qualitative benefits assumes that the benefit would be delivered for an alternative.

Figure 3. Detailed view of the cost, benefit, and risk analysis phase within the AoA proper section of the AoA framework.

The “Risk Analysis” section also includes quantitative and qualitative elements. The quantitative risk analysis uses the same assumption-driven approach as the Cost Analysis. The analysis of qualitative risks is similar to the approach for qualitative benefits. Qualitative risks are about the capability (or likelihood) of a viable alternative to deliver the solution, which was undertaken as a project to meet the business needs, as the impacts of the project.

The outcomes of the analyses conducted in Phase 2 are provided as inputs to the next phase of the framework, Conduct Decision Analysis, wherein the viable alternatives are compared to determine a recommended alternative.

1) Cost Analysis

The five steps for estimating the life cycle costs for each viable alternative typically follow the approach below; however, iterations of any step may be required to satisfy stakeholders or to address gaps in knowledge that appeared during the cost estimating process, such as when updating assumptions.

Step 1: Develop the cost element structure. Sound and defensible life cycle cost estimates for comparative analyses begin with the development of the standard cost element structure (CES) that takes into account the work breakdown structure (WBS) for the project. The CES is spread across three or four―depending upon the life cycle phases that are included in the cost estimate―major time-related phases of project costs: investment, operations and maintenance (O&M), transition costs, and, possibly, disposition costs. Investment costs capture the one time, nonrecurring costs through the Implementation phase (of the EPLC framework and see Figure 2). The O&M costs capture the recurring costs to support and maintain the system once it becomes operational. Transition costs capture the costs associated with supporting and maintaining the current legacy systems or status quo until a viable alternative achieves an established point in the O&M phase. If the life cycle cost estimate of the recommended alternative is expected to include a disposition phase, then a fourth time related phase of cost, the disposition cost, would be added to the CES.

The cost elements for each major project phase are based on all the anticipated costs required to complete an IT project over the defined life cycle. The two main cost elements within the major time related phases are products (or goods) and services, each of which can be decomposed further into sub elements and which are estimated for a WBS element. The level of detail of the final CES should be consistent with the level of detail required by the cost estimation model and approved by the project stakeholders.

Step 2: Define general and specific assumptions. Because of limited information at the time of performing the AoA, cost estimators must define assumptions that will support acceptable cost estimates and provide completeness across each viable alternative. Assumptions should address data sources (e.g., previous cost estimates, industry standards, or models), data exclusions or incompleteness (for clarification as to what was used in the cost estimation model), time frames within the project life cycle affecting cost elements, elements of scope not specifically called out in the business requirements (e.g., security categorization, availability, and performance), and methods used to calculate costs (e.g., inflation, discount rate, and capitalization).

Two types of assumptions can be defined: general and specific. General assumptions are defined for all of the viable alternatives and address elements such as the project life cycle time frame, the base year (for presentation of costs), labor rates, and the methods used for estimating costs. Specific assumptions are defined for each alternative and involve products and services that are unique to a specific alternative (e.g., allocation of software costs for the various Cloud alternatives), as well as the estimated time frames for each EPLC phase.

Step 3: Define cost estimation range approach. To produce a defensible analysis that incorporates the limitations of imperfect information and uncertainty, the approach for developing a life cycle cost model adopts the concept of cost estimation ranges. Thus, a defined assumption could have multiple outcomes typically reflecting the “best”, “worst”, and “most likely” outcomes. The “best-case” scenario captures costs based on the best-case outcome for every assumption, while the “worst-case” scenario assumes the worst-case outcome for every assumption. The “most likely” scenario captures costs that are based on the most likely outcome for each assumption. The use of the “most likely” assumption is also the definition of the risk-adjusted cost.

Step 4: Collect cost data. Cost data on each viable alternative for each cost element in the model can be gathered through several methods. The most commonly used is market research, which, according to the OMB Capital Programming Guide, encompasses “research of published information, talking to other agencies that have conducted similar market research, and/or going directly to the market for information” ( [26], p. 13). If publicly available information is not sufficient, then surveys or requests for information can be directed to qualified vendors that potentially can provide the identified viable solutions. Following the cost estimation range approach, whenever possible, data should be collected for each case scenario for each cost element. Costs gathered from historical data should be updated for inflation, technology maturity, and any other factors that may affect their value [27]. All collected cost data, including their sources and any adjustments made, should be documented.

Step 5: Estimate life cycle costs for each viable alternative. Once the assumptions have been defined and the cost data have been collected, the cost elements identified in the CES can be estimated. A variety of methods are available for estimating cost elements, among which analogy, parametric estimation, and engineering build-up estimates are the most frequently used [15] [26] [27]. Less common methods include expert opinion, extrapolating (from actual costs), and learning curves. The life cycle costs for each scenario of an alternative can be approximated by aggregating all the corresponding cost elements within each case scenario (i.e., “best”, “worst”, or “most-likely” case scenario), while recognizing the potential impact of the underlying probability impact distributions. A standard best practice uses a 10-year timeframe to represent life cycle costs [14] ; however, this timeframe may vary depending on the size, complexity, and nature of the project.

2) Benefit Analysis

The approach for the benefit analysis identifies both the quantitative and qualitative benefits anticipated to be delivered by the solution, defines the manner for estimating the benefits and collecting the necessary data, and analyzes the identified benefits for each viable alternative.

Identify benefits. All identified benefits should align with the project objectives and contribute to meeting the project business needs [26]. To allow for a comprehensive understanding of the business and mission value that the alternative would provide, both quantitative and qualitative benefits should be included.

Quantitative benefits are defined as those benefits that can be expressed in monetary units and may include both tangible and intangible benefits. Tangible benefits usually include potential direct system savings from the reduction in O&M costs for the proposed alternative relative to the O&M costs required to support the current environment and the future costs avoided by the implementation of the alternative. Intangible benefits are those benefits characterized as “not immediately obvious or measurable” ( [28], p. 22), such as potential improvements in employees’ productivity or efficiency. If they were to be clearly defined and assigned appropriate indicators or metrics, then their monetary value could be measured.

Qualitative benefits are the expected benefits generated by the alternative that are not assigned a monetary value, but nevertheless contribute to accomplishing the project objectives. Benefits produced by certain government IT projects are qualitative in nature and may not be easily or reliably quantified or monetized.

Quantitative benefits analysis. Benefits are expected to occur in the future, after the delivery of the business product by the project, and should be measured from the time the identified benefit begins to appear through the end of the project life cycle. To provide consistency in the analysis across each alternative, life cycle quantitative benefits are estimated following the same assumption-driven approach defined for the cost analysis and using the same set of assumptions specified for each of the three case scenarios: “best”, “worst”, and “most-likely”.

There are several financial metrics that can be used to analyze alternatives in terms of their overall quantitative benefits. The most commonly used metric is net present value (NPV), which OMB considers the standard for evaluating investments based on financial factors [14] [26]. In the AoA framework, the NPV of recurring costs is defined as the total present value (PV) of the recurring costs of the status quo minus the total present value of the recurring costs of the alternative. As defined, the delta indicates the estimated operational savings (as a positive value) or increases (as a negative value) of the costs that would have been incurred to maintain the status quo compared to the alternative. Other common financial metrics include internal rate of return, return on investment (ROI), benefit cost ratio, and payback period. The ROI metric calculates the projected return generated by an alternative for every investment dollar spent, in PV dollars. The payback period metric calculates the cumulative generation of projected quantitative benefits over the life cycle period relative to the cumulative costs over that same period. Unlike previously described metrics which use PV to remove inflationary factors from the calculation, the payback period metric is intended to identify the point in time when cumulative quantitative benefits exceed cumulative costs from a budgetary perspective, without regard for the time value of money.

Another metric that can be used to evaluate alternatives is the operational dollar cost per investment dollar spent or operational cost burden. It is calculated as the ratio between NPV of recurring costs, as defined above, and the PV investment costs for an alternative. With a finite life cycle period, for example 10-years, a longer investment period invariably results in a shorter duration to capture recurring costs within that 10-year timeframe. Hence, annualized costs may be preferred for this calculation.

Qualitative benefits analysis. Qualitative benefits also should be measured from the time the identified benefit begins to appear through the end of the project life cycle. To effectively measure and compare qualitative benefits across alternatives, an appropriate indicator or variable and a corresponding unit of measurement should be defined for each of the identified benefits. The data for the indicators may be obtained from contemporary data collection (e.g., market data) or from historical data from similar projects, and may require some degree of associated data analysis. After the benefits have been estimated using the same unit of measure, they can be compared directly across viable alternatives. To evaluate alternatives based on qualitative benefits measured with ordinal rating scales, a weighted-score method can be used.

3) Risk Analysis

The risk analysis approach identifies the risks potentially incurred by the viable alternatives and evaluates them from both quantitative and qualitative perspectives.

Identify risks. Risk is defined as an uncertain event or condition that, if it occurs, may have a positive or negative impact on project objectives such as time, cost, scope, and quality [29]. For each viable alternative, the relevant stakeholders should identify the risks that might impact the project and provide a clear description of the risk event. A risk that would apply equally to all viable alternatives could be excluded from the risk analysis because this risk would not contribute to a risk based distinction among all of the alternatives. Like benefits, risks can be segmented into two distinctive classifications: quantitative and qualitative. The impacts of quantitative risks are measured in financial terms. The impacts from the qualitative risks are not translated into monetary terms, but still are linked to the project successfully achieving its objectives.

Quantitative risk analysis. The objective of the quantitative risk analysis is to model the uncertainty of the primary cost drivers to determine the confidence level associated with the risk adjusted life cycle cost estimate (defined as the cost estimate of the most likely scenario generated during the cost analysis). To introduce uncertainty in the life cycle cost model, a probability of occurrence is assigned to each potential value that the assumption might take. The corresponding challenge is to determine the cost impacts linked to these probable occurrences using the currently available information for each viable alternative. The results of these calculations are a range of potential life cycle cost estimates and their respective probabilities of occurrence.

A mathematical approach to analyze uncertainty is a Monte Carlo simulation. In this approach, the uncertainty in the assumptions is captured with probability distributions. The cost model is simulated many times by random sampling of values from the probability distributions. The outcome is a probability distribution of possible life cycle cost estimates. An alternative to the Monte Carlo approach for recognizing and dealing with uncertainty, is the “3 point estimate” [27]. Within program management, as well as cost estimation, this approach is known as the Program Evaluation and Review Technique (PERT) [30] for estimating activity durations. PERT, as a 3-point estimating technique, can be used to incorporate a level of uncertainty in the cost estimates by calculating the weighted average of the three cost point estimates (“best”, “worst”, and “most-likely”), using commonly accepted probabilities of occurrence of each scenario as weights in the formula [31].

Qualitative risk analysis. One approach for the qualitative risk analysis is to use ordinal scales (e.g., low, medium, and high) to assess the probability of occurrence of the identified risks and their potential impact to the project. Then, the qualitative risks are assessed for each viable alternative by relevant project stakeholders and assigned levels for probability of occurrence and impact. The combination of the probability and impact values can be used to create a “risk score” to compare alternatives based on their overall qualitative risk.

2.2.3. Phase 3: Conduct Decision Analysis

The Decision Analysis phase provides a framework to leverage the data and information generated from the previous three separate analyses in a holistic analysis across the viable alternatives, as depicted in Figures 2-3. This analysis comprises two steps leading to a selection of a recommended alternative: identify and define a set of decision factors and then apply a weighted score method to evaluate the alternatives based on the identified decision factors.

1) Identify and Define the Project Decision Factors

The first step is to identify and define the decision factors that will be used to evaluate alternatives and select the recommended alternative to meet the project’s objectives. These decision factors should be related to functional and nonfunctional requirements identified by the project stakeholders. Their definition should include specific guidance on how to evaluate an alternative against the decision factor.

2) Evaluate the Alternatives Using a Weighted-Score Method

The second step begins with prioritizing the decision factors by assigning them weights based on their relative need or importance to the project’s goals and objectives. This activity requires broad participation and concurrence from the integrated project team to validate the project priorities; thus, minimizing bias to a singular perception or opinion. Next, each viable alternative is rated against each decision factor according to the guidance defined in the first step. Once the scoring for each alternative is complete across all decision factors, the alternative’s scores are multiplied by the corresponding decision factor’s weight and then summed to produce a weighted average score for each viable alternative. The alternative with the highest score will be the recommended alternative.

2.2.4. Phase 4: Present Recommended Alternative

In the last phase of the AoA framework, a recommendation for an alternative is presented to the relevant project stakeholders who will ultimately make the final decision. In the context of the EPLC framework, this alternative becomes the business solution to be delivered by an IT project. The decision on the recommended alternative is a decision to include the IT project into the agency’s portfolio of IT projects because it was judged to satisfy the business need, as identified, defined, and described by SMEs and other stakeholders and for which there is both an executive sponsor, who is the primary advocate for the IT project, and a viable funding strategy [32]. Therefore, the individuals or group(s) responsible for accepting the recommendation, or making the decision, should have the necessary understanding of the assumptions and AoA approach that led to the recommended alternative. They need this knowledge for proper accountability for decision making. The combination of this AoA framework inside the EPLC framework makes full transparency achievable.

The recommended alternative will be judged as most likely to support project success, as has been defined throughout the AoA framework. In the US Federal government, the recommended alternative balances and applies the decision factors in a manner consistent with the objectives of the project and the constraints of federal wide regulations and policies (e.g., “Cloud First”), DHHS mandates and policies, and CDC procedures and best practices, in a cost-effective manner that achieves the tradeoffs among costs, benefits, and risks deemed most acceptable to the federal government.

3. Application to Case Study

The case study is presented and arranged to track back to each primary section and subsection of the AoA framework, as presented above; allowing the reader to cross walk section details with how it was applied by S3P. This cross-walk capability is especially important and useful for understanding how “Cloud First” impacted the comparative analyses in the AoA. The case study can serve as guide posts for future implementations of the integrated framework approach and strengthens the authors’ model for how to disseminate methodologies and management and control practices that promote transparency and accountability by public sector managers for IT projects.

3.1. Pre-AoA: Assess Current Environment and Determine Future Environment Requirements

To assess the current environment and determine the future state S3P requirements, the project team assembled an agency-wide team of SMEs from across the functional project areas. Through Capability Modeling sessions, the SMEs identified an initial set of capabilities and evaluated their current value to program execution and how well the current environment supported the execution of the capabilities (effectiveness). In following sessions, the initial set of capabilities was refined to a total of 57, and business entities and high level process flows also were identified.

An Enterprise Architecture review of the current IT systems and projects in CDC’s IT portfolio was conducted to compare the capabilities identified by the SMEs, and required by the business, to those enabled or delivered by relevant IT systems or projects in the agency’s IT portfolio. Although the agency’s IT portfolio included more than 600 IT systems or projects, exclusion criteria systematically winnowed the status quo environment down to six currently operating information systems. Each of the 57 capabilities was evaluated in terms of its business value, current support effectiveness of the status quo, and implementation risks. Based on this analysis, the status quo environment was missing 91% of the needed functionality to address S3P goals and objectives. This 91% gap was accepted by the project team and Information Resources (IR) governance and was the basis for pursuing the business case, which incorporated the AoA.

3.2. AoA Proper

3.2.1. Phase 1: Identify and Filter Alternatives for Analysis

S3P identified 11 possible On-Premise alternatives, which included the status quo, and 12 possible Cloud alternatives (the four deployment models across the three service models). As described in this framework, two filters were defined and consecutively applied to the possible alternatives: mandatory requirements and project level (functional and nonfunctional) requirements.

The criterion for Filter 1 was the FIPS 199 Moderate security categorization assigned to the project. At the time of this AoA, no Public Cloud alternatives were able to demonstrate compliance with the FIPS 199 security requirements; thus, the Public and the Hybrid Cloud deployment models were eliminated. The remaining 16 feasible alternatives, excluding the status quo, were evaluated by the second filter.

The criteria for Filter 2 were based on the future environment requirements that were established by the IPT. There were 16 project-level decision criteria based on 9 functional and 7 non-functional requirements. Only the Private Cloud deployment model produced viable Cloud service model alternatives (i.e., SaaS, PaaS and IaaS). The On Premise alternatives, except for the status quo, were evaluated against each of the project level decision criteria and then ranked based on their aggregated weighted scores. The outputs of Filter 2 were six viable alternatives: the status quo, two On-Premise alternatives, and three Private Cloud alternatives.

The PaaS and IaaS Private Cloud alternatives required a special consideration for how the solution would be obtained, which increased the viable Cloud alternatives to five: one SaaS, two PaaS, and two IaaS alternatives.

The final set of viable alternatives included the status quo plus seven new alternatives, as depicted in Table 2. Further market research on the seven new alternatives provided the sufficient information to perform the cost, benefit, and risk analysis in the subsequent phase of the AoA framework.

3.2.2. Phase 2: Conduct Cost, Benefit, and Risk Analysis of All Viable Alternatives

S3P conducted cost, benefit, and risk analyses on the final viable alternatives (cf. Table 2) that emerged from the phase titled “Identify and Filter Alternatives for Analysis” (cf. Figure 2).

1) Cost Analysis

For the life cycle cost estimation, cost elements for products and services were grouped in three time related phases: a) investment, b) operations and maintenance, and c) transition costs. General assumptions included the project management structure, inflation rate, and government salary costs. Specific assumptions

Table 2. S3P alternatives that were identified as possible, feasible, and viable for the AoA.

Note. SQ = Status Quo. USQ = Updated Status Quo. COTS = Commercial Off-The-Shelf. GOTS = Government Off-The-Shelf. SIPS = Suite of Integrated Products and Services. CB = Custom Build. Individual (Ind) is defined as a solution of various components or vendor products that may have integration points but each of these components or products operates independently. Integrated (Int) is defined as a solution of various components or vendor products that are fully integrated and operate as a “single” cohesive unit as viewed by the end user. aOn-Premise Computing is defined as a computing model, Cloud or not, that deploys locally at the consumer organization. bCloud Computing delivers computing services and technologies matched to acute and/or dynamic thresholds of need types established by the user of the services and technologies [33]. c“How” the solution will be obtained is described in the subsection “Identify Possible Alternatives.”

developed for each viable alternative included the time frames for each EPLC phase, the level of software application customization, and the number of contractor hours. All assumptions and ground rules were reviewed by the S3P IPT and the Critical Partners (CPs) and approved by the project leadership. S3P estimated the range, defined by the lower bound (i.e., “best-case”), upper bound (i.e., “worst-case”) and risk-adjusted (i.e., “most-likely case”) estimates, of PV 10-year life cycle costs for each viable alternative.

The PV lower bound 10 year life cycle cost estimate for the SaaS Private Cloud alternative was the least costly, followed by the SIPS On-Premise alternative; the most expensive PV lower bound cost estimates occurred for the custom developed applications in the PaaS and IaaS Private Cloud environments.

The following conclusions were drawn during the cost (sensitivity) analysis: the largest cost driver was the time component of labor costs. Since labor costs involve duration of effort, or time, the overall life cycle costs were reflective of the total amount of time estimated to deliver the solution, and the greater the degree of customization, the greater the development and integration costs. The third impact on labor costs was requirements specificity: more loosely defined (and accepted) requirements introduce more uncertainty into cost estimating compared to modeling based on requirements that are well understood and amenable to the cost estimation method.

2) Benefit Analysis

S3P identified and analyzed both quantitative and qualitative benefits for all viable alternatives. To determine if any system savings existed, the O&M costs of the status quo was compared to the O&M costs of each of the other viable alternatives. This comparison indicated that none of the viable alternatives generated savings, even accounting for various O&M durations within the 10 year life cycle cost estimate: the status quo O&M costs were approximately an order of magnitude less than any of the O&M costs of any alternative. The operational cost per investment dollar was analyzed without annualizing it. The smallest cost burden was observed for the SaaS Private Cloud alternative, as the O&M component of the recurring costs―regardless of upper, lower, or risk adjusted―was the least among all of the alternatives. Overall, the operational cost burden of the Cloud alternatives was less than the On Premise alternatives, but remember that this ratio obscures the actual magnitudes of the numbers forming the ratio, indicating the importance of multiple types of analyses for recommending the alternative to carry forward.

A total of ten qualitative benefits were identified from three sources: key benefits identified across alternatives, qualitative benefits captured within the project critical success factors (CSFs), and benefits determined by the S3P IPT/CPs. As depicted in Table 3, each benefit was assigned an importance value (or weight) of Minimal (1), Moderate (2), Moderate/High (3) or High (4). After assessing each alternative against each benefit, the overall capability of each of the Cloud solutions (weighted average range: 9.0 - 10.0) was judged to be superior compared to the On Premise solutions (weighted average range: 8.6 - 8.9).

Table 3. Ten benefits assessed for each viable alternative.

3) Risk Analysis

S3P identified potential risks areas and assessed them from a quantitative or qualitative perspective. In the quantitative risk analysis, the objective was to assess how well the risk adjusted life cycle cost estimates captured the uncertainty associated with the risk factors. The outcomes of the Monte Carlo simulations were that the risk-adjusted life cycle costs for the On-Premise SIPS alternative were associated with the highest level of confidence of 91%, followed by the PaaS Custom Build alternative at 80.2%. The alternatives with the lowest level of confidence in their risk-adjusted cost estimates were the IaaS Custom Build, IaaS SIPS, and On Premise Custom Build alternatives at 20.7%, 27.4% and 44.6% confidence levels, respectively.

The following identified risk areas were assumed to have no direct financial impact on the project and therefore addressed through a qualitative risk analysis:

・ Overall Project Failure: The risk of the solution ultimately becoming “unimplementable”.

・ Information System Security: The risk of increased level of effort needed to ensure that the information system security requirements are met.

・ Stakeholder/Business Owner: The risk of weak, ineffective, or waning stakeholder buy-in and commitment through the Operations and Maintenance phase.

・ Technology: The risk that the rapid evolution of technology can create for S3P.

・ Compliance: The risk that the solution would not be able to satisfy the S3P mandatory requirements.

For each identified risk area, the combination of impact and probability generated a risk score for each alternative. Based on this analysis, the On-Premise SIPS alternative scored the lowest overall qualitative risk, followed by the On-Premise Custom Build option. On the other side of the spectrum, the Cloud alternatives scored the highest overall qualitative risk.

3.2.3. Phase 3: Conduct Decision Analysis

Under the S3P AoA Decision Analysis framework, the S3P IPT identified six decision factors, weighted as depicted in Table 4, to evaluate the viable alternatives, as reviewed below.

1) Ability to meet critical success factors: The functional and nonfunctional CSFs were used to establish the viable alternatives during Step 2 (Filter 2) of “Filtering for Viable Alternatives”. This decision factor was the second most important factor identified by the project team. Apart from the status quo, each of the viable alternatives was confirmed to be able to successfully meet all of the CSFs and was assigned a High score (4).

2) Number of years in planning through implementation EPLC phases: Under the AoA, the cost analysis captured a 10-year life cycle comprised of different times in EPLC Planning through Implementation phases, or the investment period, and then the O&M phase. Each viable alternative was ranked based on the

Table 4. Six decision factors and weights for the arriving at the recommended alternative in the decision analysis.

duration of the investment period. The shortest investment period was estimated for On-Premise SIPS and was assigned a Moderate/High score (3). The On-Premise Custom Build was assigned a score of 2. All Cloud alternatives received the Low score (1).

3) Total present value risk-adjusted life cycle costs: The total present value risk-adjusted life cycle costs for each alternative were scored. This cost was the least for the status quo, scored a 4, followed by the two On Premise alternatives of SIPS and Custom Build of 3 and 2 respectively. The Cloud alternatives were the most costly.

4) Qualitative risks: Qualitative risks were the most important in the decision analysis process. Qualitative risks were deemed most favorable (High or 4) for the On-Premise SIPS alternative, followed by the On Premise Custom Build alternative at Moderate/High (3), and then least favorable (Low or 1) for all of the Cloud alternatives.

5) Qualitative benefits: Qualitative benefits scores were tightly bunched among all of the alternatives, save for the status quo and the IaaS alternatives. Each of the On Premise SIPS and SaaS alternatives were judged to deliver the greatest collection of benefits. The On Premise Custom Build and remaining Cloud alternatives were approximately of similar benefit.

6) Confidence level of total PV risk-adjusted life cycle costs: The uncertainty analysis within the Risk Analysis calculates a level of confidence indicating the degree to which the risk-adjusted cost estimate captured the impact of identified risks within the cost analysis. The On-Premise SIPS alternative was assigned a High score (4), followed by the two PaaS alternatives each with a score of 3 (80th - 89th percentile). The cumulative probability distributions associated with the risk adjusted costs for the other alternatives were below the 69th percentile and assigned the Low (1) score.

3.2.4. Phase 4: Present Recommended Alternative

The work of the entire AoA is encapsulated in Table 5 as a single deliverable that packages together and displays the objective of this framework: to systematically examine the included viable alternatives as potential business solutions to

Table 5. The S3P case study to illustrate the decision analysis.

Note. NA = Not Applicable. SQ = Status Quo. SIPS = Suite of Integrated Products and Services. CB = Custom Build. COTS = Commercial Off-The-Shelf. Cell values are weighted scores. Larger values are more favorable. aSee Table 1 for explanation of Cloud service models.

meet the business need in order to provide a recommended alternative for IR governance to accept, which in turn will lead to an IT project to deliver the recommended alternative as the business solution. In the S3P case study, the overall weighted score for the On-Premise SIPS alternative was observed to be distinctly different from the other viable alternatives. The primary decision factor accounting for this difference was the qualitative risks. Qualitative risks have the potential to derail a project and were judged to be the most important factor for decision making. Because the S3P AoA was conducted during 2011, when the US Federal government was only on the cusp of implementing the “Cloud First” policy, SMEs and stakeholders determined that risks such as overall project failure, information system security, long running stakeholder participation and commitment, hype cycle impact on technology enthusiasm, and achieving compliance with all mandatory requirements would be less risky with an On Premise deployment. The second distinguishing factor in Table 5 is the cost: not only was the SIPS solution less costly, but there was more confidence in the cost estimate. Thus, the S3P project team recommends the On-Premise SIPS alternative to IR governance at the stage gate review for the Concept phase of the EPLC framework.

4. Discussion

The purpose of this paper was to illustrate a framework for completing an AoA for an IT project in support of an information system strategy. We used an IT project in an operating division of DHHS to illustrate how to answer the questions of 1) what is the recommended alternative; and 2) should the recommended alternative be based on cloud computing. Of particular interest in the case study was the application of the AoA framework when Cloud computing alternatives were included among the viable alternatives. The integration of the two frameworks offered a roadmap beyond impediments to how to formulate an actual selection decision that could lead to a Cloud computing implementation. The case study illustrated the integration of these two frameworks and resulted in a defensible position with regard to the “Cloud First” policy for the recommended alternative. Importantly, and in addition, the AoA framework was careful to emphasize and note that the decision for the recommended alternative is far removed from just a cost focus, and in fact, should be based on and represent the priorities and points of view of the IPT for the benefits to be realized and risks to be managed for the delivery of the recommended alternative as the business solution. This paper illustrated how the combination of the AoA and EPLC frameworks makes it possible to achieve these objectives while meeting all federal requirements for benefit-cost analysis [14], budget preparation [15], and conforming to best practices for cost estimation and assessment [27].

This paper articulates the EPLC framework established by policy [2] [3] with a set of four process, as depicted in Figure 2 and developed further in Figure 3. This set of four processes comprises the AoA Proper section of the entire AoA framework. An important contribution of this articulation is the establishment of the eventual set of viable alternatives based on project objectives and subsequent capabilities (in the Pre-AoA section) required by SMEs who will be using the implemented solution. The time phased articulation with the EPLC framework both during the Concept as well as O&M phases is an important distinction and difference versus the AoA framework as a standalone effort. This time phased articulation enriches both frameworks by bringing techniques and outputs from one to bear upon the other.

As noted above, the AoA framework described in this paper is the logical organization of actions producing value to the project as the recommended and defensible path forward. This value arises from not conducting the analysis as a separate, standalone effort, but as a work stream integrated and articulated with the overall project work. This view of the AoA framework in the context of the project purpose and the impact of environmental factors, such as “Cloud First”, is a unique aspect and contribution of this work and can provide practitioners with techniques for project management in the federal government context.

Although the “Cloud First” policy appeared on the horizon of the US Federal government within the recent decade (i.e., circa 2011), authors with a historical view of Cloud computing point out that it might be more accurate to view Cloud computing as an evolution to its current state rather than as a computing model with a clear, trigger event ( [35], p. 12-13), because Cloud computing “is based on … many old and [a] few new concepts” ( [36], p. 1). The specific new concepts applicable to “Cloud First” are based on delivering computing services and technologies matched to acute and/or dynamic thresholds of need types established by the user of the services and technologies as provided by Cloud computing [20] [33]. The concept of a Cloud computing taxonomy is useful because it informs or even specifically identifies Cloud alternatives in an IT AoA. EPLC is not a collection of decision frameworks, but it is marked by a series of “Go No-Go” governance decisions at phase boundaries, as indicated by the triangles and diamonds in Figure 1. Systematic approaches for developing recommendations for a governance decision often occur throughout the EPLC framework, as required by the project and its stakeholders, and invariably compare the costs, benefits, and risks associated with a set of choices or alternatives. This paper formalizes the systematic integration of a sub work stream, the AoA, into the overall project management effort. The case study brings AoA details to a greater understanding via the application and illustration of analyses with actual evidence and data.

The “Cloud First” policy says that if the Cloud alternative is secure, reliable, and cost effective, then it must be the recommended alternative for delivering the IT product. The “Cloud First” policy is an information system strategy of the US Federal government. Government guidance, following and flowing from “Cloud First”, appeared in 2012 as the Federal Data Center Consolidation Initiative (FDCCI) [37]. More recently, FDCCI was targeted for special monitoring in 2015 [38] under the implementation of the Federal Information Technology Acquisition Reform Act (FITARA) of 2014 [39]. As noted at beginning of this paper, efficient use and stewardship of public funds was a fundamental driver of the policy and the subsequent codification in FITARA. One of the early steps in the achievement of the goals set out by this information system strategy is the capability to make the defensible decision for how to deploy the technical solution. Our paper brings together the essential frameworks for how to arrive at the necessary and required defensible decision.

In terms of arriving at the defensible decision for the S3P solution deployment, the AoA framework allowed S3P specifically to address each of these decision making criteria. The first filter in the framework, for the application of mandatory requirements, made it possible to ensure that federal information security requirements would be met by all alternatives passing through this filter. As reviewed and accepted by S3P Critical Partners, the Private Cloud deployment model was capable of meeting FIPS 199 processing standards, and, thus, the three service models within the Private Cloud deployment model became viable candidates. The “Cloud First” criterion of reliability was contained with the project level criteria, and as documented in the S3P case study, the three Cloud service models met it. However, as shared in Table 5, the Cloud alternatives were not judged to be cost-effective, as defined via the decision factor analysis. Thus, the S3P AoA was completed and guided by the “Cloud First” policy, but the evidence led to an On Premise recommendation, as guided by the “Cloud First” decision criteria.

The “Cloud First” policy arrived after and also had a context with Transparency and Open Government [40]. To achieve the objective of open government, the Administration sought to establish a system of “transparency, public participation, and collaboration”. “Cloud First” also sought to promote public participation and collaboration with the US Federal government in order to achieve the Cloud benefits enumerated in the policy. Inherently, transparency, public participation, and collaboration can strengthen accountability. While the technical aspects of the AoA framework provide practices and methods that can deliver a defensible recommendation, broad, collaborative participation within a government agency yields transparency and accountability for use of public funds, which in this case was for a project designed to provide public health and safety services to its citizens. As a matter of accountability, direction should be subject to evaluation. Not only does “Cloud First” represent a direction, but so does pursuing the recommended alternative (from the AoA framework) as the solution to meet the business need.

5. Conclusion

To summarize, the implementation of an AoA framework within the context of federal IT project management was presented in this paper. The AoA EPLC integration is a coupling of methodology with management and control practices that can promote transparency and accountability by public sector managers for IT projects. This AoA framework is adaptable and extensible. The AoA framework makes it possible to respond to pressures from a variety of environmental factors, such as driven by federal regulations and policies or a technology hype cycle [41], with defensible conclusions. The incorporation of “Cloud First” demonstrated the capability of the AoA EPLC integration to meet a new federal government direction as an information system strategy. The AoA framework also provides a starting point for evaluative research because the framework systematically addresses and documents the steps taken by public sector managers to arrive at the AoA objective. An evaluative commitment, made possible by the framework, ultimately shapes and drives performance by the nature of accountability. Thus, a value of this AoA is that it underpins defensible IT project management.

Disclaimer

The findings and conclusions in this manuscript are those of the author(s) and do not necessarily represent the official position of the US Centers for Disease Control and Prevention.

Acknowledgements

Portions of the paper were written when the first author was an Oak Ridge Institute for Science and Education (ORISE) fellow. The analytic framework was developed when the second author was under contract to support the Science Services and Support Project for the Office of the Associate Director for Science. However, the paper was written subsequent to the delivery of those services and was not a contractual deliverable. The authors acknowledge Tyler Higgins for his contributions to earlier drafts of this manuscript.

Conflicts of Interest

The authors declare no conflicts of interest.

References

[1] Office of the Associate Director for Science (2012) Science Services Support Project (S3P) Business Case. Centers for Disease Control and Prevention, Atlanta.
[2] Department of Health and Human Services (2016) Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC). US Department of Health and Human Services: Office of the Chief Information Officer, Washington DC.
https://www.hhs.gov/sites/default/files/eplc-policy-dec-2016.pdf
[3] Department of Health and Human Services (2008) HHS OCIO Policy for Information Technology (IT): Enterprise Performance Life Cycle (EPLC). US Department of Health and Human Services: Office of the Chief Information Officer, Washington DC.
http://www.hhs.gov/ocio/policy/2008-0004.001.html
[4] Enterprise Performance Life Cycle Framework Workgroup (2010) Enterprise Performance Life Cycle Framework: Overview Document. Department of Health and Human Services: Office of the Chief Information Officer, Washington DC.
http://www2.cdc.gov/cdcup/library/hhs_eplc/EPLC_Framework_01-25-10.pdf
[5] Office of Management and Budget (2012) Circular No. A-11: Preparation, Submission, and Execution of the Budget. Executive Office of the President, Office of Management and Budget, Washington DC.
http://www.whitehouse.gov/omb/circulars_a11_current_year_a11_toc
[6] 104th Congress (1996) Clinger-Cohen Act.
[7] Kundra, V. (2010) 25 Point Implementation Plan to Reform Federal Information Technology Management. Office of Management and Budget, Office of E-Government and Information Technology, Washington DC.
[8] Government Accountability Office (2009) Many Analyses of Alternatives Have Not Provided a Robust Assessment of Weapon System Options. Government Accountability Office, Washington DC.
http://www.gao.gov/products/GAO-09-665
[9] Office of Aerospace Studies (2008) Analysis of Alternatives (AoA) Handbook: A Practical Guide to Analyses of Alternatives. Office of Aerospace Studies.
[10] Federal Acquisition Institute (2015) Project Manager’s Guidebook. Federal Acquisition Institute.
https://www.fai.gov/drupal/sites/default/files/FAI-Project-Managers-Guidebook.pdf
[11] Indian Health Services (2008) Managing Capital Investments at the Indian Health Service: A “How-To” Guide for an Analysis of Alternatives. Indian Health Services.
[12] US Department of Defense (2015) Operation of the Defense Acquisition System.
http://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodi/500002_dodi_2015.pdf?ver
=2017-08-11-170656-430
[13] Kundra, V. (2011) Federal Cloud Computing Strategy. Office of Management and Budget, Office of E-Government and Information Technology, Washington DC.
[14] Office of Management and Budget, Washington DC (1992) Circular No. A-94: Guidelines and Discount Rates for Benefit-Cost Analysis of Federal Programs. Office of Management and Budget, Washington DC.
https://www.whitehouse.gov/sites/whitehouse.gov/files/omb/circulars/A94/a094.pdf
[15] Office of Management and Budget (2008) Circular No. A-11 Part 7 Planning, Budgeting, Acquisition, and Management of Capital Assets. Executive Office of the President, Office of Management and Budget, Washington DC.
http://www.whitehouse.gov/omb/circulars_a11_current_year_a11_toc
[16] United States Government Accountability Office (2012) Information Technology Reform: Progress Made but Future Cloud Computing Efforts Should Be Better Planned. Washington DC.
https://www.gao.gov/products/GAO-12-756
[17] Alkhalil, A., Sahandi, R. and John, D. (2017) An Exploration of the Determinants for Decision to Migrate Existing Resources to Cloud Computing Using an Integrated TOE-DOI Model. Journal of Cloud Computing, 6, 2.
[18] Cardoso, A., Moreira, F. and Simões, P. (2014) A Survey of Cloud Computing Migration Issues and Frameworks. In: Rocha, A., Correia, A.M., Tan, F.B. and Stroetmann, K.A., Eds., New Perspectives in Information Systems and Technologies, Volume 1, Springer, Berlin, 161-170.
[19] Elena, G. and Johnson, C.W. (2015) Factors Influencing Risk Acceptance of Cloud Computing Services in the UK Government. International Journal on Cloud Computing: Services and Architecture, 5, 1-16.
http://airccse.org/journal/ijccsa/papers/5315ijccsa01.pdf
[20] Figliola, P.M. and Fischer, E.A. (2015) Overview and Issues for Implementation of the Federal Cloud Computing Initiative: Implications for Federal Information Technology Reform Management. US Congressional Research Service (CRS), Washington DC.
[21] Greer, M. (2015) FITARA and FedRAMP: Accelerating Federal Cloud Adoption. IEEE Cloud Computing, 2, 48-52.
https://doi.org/10.1109/MCC.2015.90
[22] Jackson, K.L. (2015) IEEE GovCloud: Making a Difference for Global Governments. IEEE Cloud Computing, 2, 54-59.
https://doi.org/10.1109/MCC.2015.81
[23] Department of Health and Human Services (2003) HHS IRM Policy for Conducting Information Technology Alternatives Analysis. US Department of Health and Human Services: Office of Information Resources Management, Washington DC.
[24] Mell, P. and Grance, T. (2011) The NIST Definition of Cloud Computing. National Institute of Standards and Technology, Gaithersburg.
[25] Stine, K., Kissel, R., Barker, W.C., Fahlsing, J. and Gulick, J. (2008) Volume I: Guide for Mapping Types of Information and Information Systems to Security Categories. NIST Special Publication 800-60 Volume I Revision 1, National Institute of Standards and Technology, Gaithersburg.
[26] Office of Management and Budget (2012) Capital Programming Guide v 3.0: Supplement to Office of Management and Budget, Washington DC Circular A-11 Planning, Budgeting, and Acquisition of Capital Assets. Executive Office of the President. Office of Management and Budget, Washington DC.
[27] Government Accountability Office (2009) GAO Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs. Government Accountability Office, Washington DC.
http://www.gao.gov/new.items/d093sp.pdf
[28] Capital Planning and IT Investment Committee (1999) ROI and the Value Puzzle. Federal Chief Information Officers Council.
http://enos.itcollege.ee/~linnar/IT-ROI/roi.pdf
[29] Project Management Institute (2008) A Guide to the Project Management Body of Knowledge (PMBOK Guide). 4th Edition, Project Management Institute, Inc., Newtown Square.
[30] Stauber, B.R., Douty, H.M., Fazar, W., Jordan, R.H., Weinfeld, W. and Manvel, A.D. (1959) Federal Statistical Activities. The American Statistician, 13, 9-12.
https://doi.org/10.1080/00031305.1959.10482609
[31] Project Management Institute (2013) Software Extension to the PMBOK Guide. 5th Edition, Project Management Institute, Inc., Newtown Square.
[32] Enterprise Performance Life Cycle Framework Workgroup (2012) Enterprise Performance Life Cycle Framework: Overview Document. Department of Health and Human Services: Office of the Chief Information Officer, Washington DC.
http://www2.cdc.gov/cdcup/library/hhs_eplc/EPLC_Framework_09-18-12.pdf
[33] Kaisler, S., Money, W.H. and Cohen, S.J. (2012) A Decision Framework for Cloud Computing. Proceedings 45th Hawaii International Conference on System Sciences, Hawaii, 1553-1562.
https://doi.org/10.1109/HICSS.2012.52
[34] Schank, J.F. (2012) Analysis of Alternatives: Keys to Success. Ninth Annual Acquisition Research Symposium, Graduate School of Business & Public Policy at the Naval Postgraduate School.
[35] Rhoton, J. (2009) Cloud Computing Explained: Handbook for Enterprise Implementation. Recursive Press, London.
[36] Youseff, L., Butrico, M. and Da Silva, D. (2008) Toward a Unified Ontology of Cloud Computing. Proceedings Grid Computing Environments Workshop, Austin, 12-16 November 2008, 1-10.
https://doi.org/10.1109/GCE.2008.4738443
[37] Office of Management and Budget (2012) Implementation Guidance for the Federal Data Center Consolidation Initiative (FDCCI). Executive Office of the President, Office of Management and Budget, Washington DC.
https://www.whitehouse.gov/sites/whitehouse.gov/files/omb/assets/egov_docs/
cio_memo_fdcci_deliverables_van_roekel_3-19-12.pdf
[38] Office of Management and Budget (2015) Management and Oversight of Federal Information Technology. Executive Office of the President, Office of Management and Budget, Washington DC.
https://www.whitehouse.gov/sites/whitehouse.gov/files/omb/memoranda/2015/m-15-14.pdf
[39] 113th Congress (2104) Federal Information Technology Acquisition Reform. US Government Publishing Office, Washington DC.
[40] Obama, B. (2009) Transparency and Open Government: Memorandum for the Heads of Executive Departments and Agencies. The White House, Washington DC.
https://obamawhitehouse.archives.gov/the-press-office/transparency-and-open-government
[41] Fenn, J. (2008) Understanding Gartner’s Hype Cycles, 2008.
http://www.gartner.com