PERT and CPM in Project Management with Practical Examples

HTML  XML Download Download as PDF (Size: 923KB)  PP. 215-226  
DOI: 10.4236/ajor.2021.114013    2,764 Downloads   52,526 Views  Citations

ABSTRACT

This paper reviewed the concepts of Project Evaluation Review Technique and Critical Path Method in project management with practical examples. The methods and success of quantitative decision-making approaches in project management through the use of project evaluation review technique and the critical path method as regards project duration and critical activities of a project, were discussed. The review found that while both methods are effective in achieving success in project management, the relationship and connectivity of activities involved in a project life cycle are key aspects. The paper concludes that the project evaluation review technique is more effective when the duration of the project is uncertain, while the critical path method is effective when the project’s end time is certain. The paper, therefore, recommends that to achieve maximum operative efficiency in utilizing resources in project management, prior to commencing the execution of a project, all required resources to cover every activity must be assembled and prioritized to eliminate interruptions that could bring delay and unnecessary cost implications. Again, policies focused on improving project execution should be implemented in developing nations to minimize the many cases of failed and delayed projects. Subsequently, stakeholders in projects must be given the right, under the law, to prosecute the government, its agencies and/or the executors of projects for failure to execute a project on schedule.

Share and Cite:

Bagshaw, K. (2021) PERT and CPM in Project Management with Practical Examples. American Journal of Operations Research, 11, 215-226. doi: 10.4236/ajor.2021.114013.

Cited by

[1] Utilization of fuzzy critical path method and fuzzy program evaluation and review technique for building a hydroelectric power station
Dutse Journal of Pure and Applied …, 2022
[2] Application of Project Time Management and Resource Management to a Novel Blended Wing Unmanned Aerial Vehicle (BWB UAV) Design
Open Access Library Journal, 2022
[3] استعمال تقنيات إدارة المشاريع فى إنجاز أطروحة الدكتوراه حسب نظام LMD‎
المجلة الجزائرية للعلوم الإجتماعية والإنسانية, 2022
[4] Perancangan Jadwal Proyek FTTH (Fiber To The Home) Menggunakan Metode Critical Path Method Studi Kasus Pada PT XYZ
eProceedings …, 2021
[5] A Systematic Literature Review: Optimization of Implementation of Project Development in the Company with PERT and CPM Method
[6] Philippine Public Senior High School Time Optimization of School Forms Preparation

Copyright © 2024 by authors and Scientific Research Publishing Inc.

Creative Commons License

This work and the related PDF file are licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.